Inkers
Case Study · Residential

How two towers avoided ₹14 crore in overruns before construction began

Two B+G+25 luxury towers where NBC, services coordination, BOQ, and area discipline were locked down at drawing stage — averting a 4–6 month delay and ₹9–14 Cr in overruns.

Powered by Kael
Two residential high-rise towers under construction

4–6 mo

Handover delay closed

₹9–14 Cr

Cost overrun (5–8%) averted

6 lakh sq ft

B+G+25 across 2 towers

Project Brief

Structure

2 Towers, B+G+25

Total Saleable Area

6,00,000 Sq Ft

(3 lakh per tower)

Project Cost

₹180 Crore

(₹3,000 per sq ft constr.)

The brief

Two B+G+25 luxury residential towers, ₹180 Cr in capex, 6 lakh sq ft of saleable area split evenly across the two structures. The developer's promise was a rigid handover date — and the financial model assumed that anything caught after structure would be priced as a change order.

Why it was risky

Residential luxury sits on the most unforgiving margin of any asset class: buyers measure carpet area to the centimetre, and any post-structural change to core or services compounds across every floor.

  • NBC non-compliance in core, stair, lift, and refuge layouts is the canonical late surprise. It typically arrives during occupation certificate review and forces post-structural redesign.
  • Services mis-coordination between architectural and MEP packages creates wet-area conflicts that don't surface until plumbing first-fix.
  • BOQ omissions for builder's works (MEP penetrations, façade backing) are absorbed as change orders at vendor-favourable rates.
  • Area mismatches of even 1–2% between RERA carpet, structural drawings, and marketing collateral land in court.

What Kaël did

  • Ran NBC and core compliance continuously against the latest GFC drawings, holding the structural team to the regulation envelope rather than letting late approvals catch the mistake.
  • Detected micro-clashes between MEP risers, slabs, and beams in wet areas, weeks ahead of plumbing first-fix.
  • Cross-checked BOQ versus design intent so the contractor's commercial team couldn't claim scope gaps that should have been costed at tender.
  • Flagged area drift at the drawing stage — every 1% of carpet variance was reported with the financial impact calculated at sale price.

Outcome

The 4–6 month handover delay risk priced into the schedule was closed before foundation work was complete. ₹9–14 Cr of cost overrun (5–8% of total project cost) — the band the developer had reserved for late surprises — was returned to the contingency line.

Impact

4–6 Months

Delay in completion and handover

₹9–14 Cr

Cost overrun (5–8%)

Construction is changing. Are you?

We work closely with every client to understand the specific project before anything else. Tell us what you're building.